Production Downtime Report

Production downtime report measures the duration and cost of downtime for a production resource, operation, and work center. Both planned and unplanned downtime are measured, and cost is calculated based on the cost per unit of time and total downtime.

Downtime is tracked from start of an operation until the operation is completed. Downtime sums all of the snippets when operation was suspended during operational hours. Downtime that overlaps with non-operational hours is not counted in this report.

Note: This report only shows breakdown for costs of production tasks, not assembly tasks. Components are not listed. To show an analysis of costs per component for assembly and production tasks, see Production Cost Analysis.

Users need the Production Reporting permission to access this report.

Before you start

Data from this report can be exported in Excel, PDF or RTF format.

Input:

Input Description
Reporting Period Allow user to select the reporting period from a list of options or set a custom date range.
Layout Set to the Default layout. Allows selection of saved layouts, if any.
Save Layout As Allows saving of a layout for potential future use.
Reset Layout Resets layout to the default layout or selected saved layout.
Show In Show downtime in seconds, minutes, or hours.

Select Apply Filter to set filter fields for the report and Update to refresh the output with any new changes. See Managing Cin7 Core Reports - Filtering Reports for more detailed information about using filters.

Output:

The following output fields are available for this report. You may have to open the Configure Layout menu to add some of them to your report.

Fields

Field Description
Location Production location (Shopfloor).
Type Type of suspend reason: Planned, Not Planned, or Undefined.
Reason Suspend reason for operation.
Work Center Work Center for the suspended production operation.
Operation Production operation.
Run # Production run number.
Order # Production order number.
Resource Resource used in the production process.
Status Production run status.
Year Year of suspension.
Version Bill of Material version number. Applies only to Production and Make to Order BOM. Default version is marked.
Production Additional Attribute 1-10 Value of additional production attributes.

Data headers

Data header Description
Downtime Total amount of downtime in seconds, minutes, or hours.
Downtime Costs Total cost of downtime.

Was this article helpful?

Have more questions? Submit a request