Production Downtime Report

Production Downtime Report

Production downtime report measures the duration and cost of downtime for a production resource, operation, and work center. Both planned and unplanned downtime are measured, and cost is calculated based on the cost per unit of time and total downtime.

Downtime is tracked from start of an operation until the operation is completed. Downtime sums all of the snippets when operation was suspended during operational hours. Downtime that overlaps with non-operational hours is not counted in this report.

Note: This report only shows breakdown for costs of production tasks, not assembly tasks. Components are not listed. To show an analysis of costs per component for assembly and production tasks, see Production Cost Analysis.

Users need the Production Reporting permission to access this report.

Prerequisites

 

 

Data from this report can be exported in Excel, PDF or RTF format.

Input:

Reporting Period

Allow user to select the reporting period from a list of options or set a custom date range.

Layout

Set to the Default layout. Allows selection of saved layouts, if any.

Save Layout As

Allows saving of a layout for potential future use.

Reset Layout

Resets layout to the default layout or selected saved layout.

Show In

Show downtime in seconds, minutes, or hours.

 

Select Apply Filter to set filter fields for the report and Update to refresh the output with any new changes. See Managing Cin7 Core Reports - Filtering Reports for more detailed information about using filters.

Output:

The following output fields are available for this report. You may have to open the Configure Layout menu to add some of them to your report.

Fields

Location

Production location (Shopfloor).

Type

Type of suspend reason: Planned, Not Planned, or Undefined.

Reason

Suspend reason for operation.

Work Center

Work Center for the suspended production operation.

Operation

Production operation.

Run #

Production run number.

Order #

Production order number.

Resource

Resource used in the production process.

Status

Production run status.

Year

Year of suspension.

Version

Bill of Material version number. Applies only to Production and Make to Order BOM. Default version is marked.

Production Additional Attribute 1-10

Value of additional production attributes.

Data Headers

Downtime

Total amount of downtime in seconds, minutes, or hours.

Downtime Costs

Total cost of downtime.

Was this article helpful?

Have more questions? Submit a request